The Senate Standing Committee on Power Division on Wednesday informed that work on all three lots including Dasu Hydropower Project, Mansehra Sub Station and Islamabad Sub Station has already been started. The committee which met with Senator Saifullah Abro in the Chair was told that the total length of the transmission line was 254.6 kilometres which included 686 towers, the state news agency reported.

 